PgMP Demo and Sample
Note: Answers are below each question.
Samples are taken from full version.
Latest PgMP Exam Questions and Practice Tests 2024 - Killexams.com
PgMP Dumps PgMP Braindumps
PgMP Real Questions PgMP Practice Test PgMP Actual Questions
PMI
PgMP
PgMP
https://killexams.com/pass4sure/exam-detail/PgMP
QUESTION: 330
Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?
Crash the program
Add lead time to the program
Trim the program scope
Fast track the program
Answer: D
QUESTION: 331
Which of the following is described in the statement given below?
"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."
Governance plan
Organizational chart
Program scope statement
Stakeholder register
Answer: D
QUESTION: 332
A project manager in your program has estimated the cost of a program to be
$145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?
Gold plating
Value added change
Expert judgment by the project manager
Errors and omissions
Answer: A
QUESTION: 333
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?
Cost, because the program has an estimate to complete of $1,151,429.
Cost, because the program has a cost variance of -7,500
Schedule, because theprogram's planned value is only $700,000.
Schedule, because the program has a schedule performance index of .88.
Answer: D
QUESTION: 334
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
Business case
Scope statement
Requirements document
Project charter
Answer: B
QUESTION: 335
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?
Planning
Scope verification
Quality control
Quality assurance
Answer: D
QUESTION: 336
A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
Program benefits
Link to organizational strategy
Program scope
Program risk
Answer: D
QUESTION: 337
You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?
It is the review of the impact of the change on the program's triple constraints.
It is the review of the impact of the change on the time, cost, scope, and quality baselines.
It is the review of the impact of the change on the program's Iron Triangle.
It is the review of the impact of the change on the program's knowledge areas.
Answer: D
QUESTION: 338
You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?
Payback period
Cost-to-benefits ratio
Cost performance index
Return on investment
Answer: A
QUESTION: 339
Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?
The program scope has changed.
The project scope has changed from the original intent of the project
The scope is not being met as planned due to scope creep.
The project resources are not completing their project tasks as assigned.
Answer: A
QUESTION: 340
An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?
A. $1,158,250
B. It depends on the internal decision making process. C. $1,550,000
D. $2,074,249
Answer: A
QUESTION: 341
Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?
Sign the certificate of program closure
Complete the program's budget
Release the program's resources
Close the constituent projects before closing the program
Answer: A
QUESTION: 342
You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?
Lessons learned are created at each program deliverable.
Lessons learned are created during the program closure.
Lessons learned are created during the program archive.
Lessons learned are in program execution.
Answer: B
6$03/( 48(67,216
7KHVH TXHVWLRQV DUH IRU GHPR SXUSRVH RQO\ )XOO YHUVLRQ LV XS WR GDWH DQG FRQWDLQV DFWXDO TXHVWLRQV DQG DQVZHUV
.LOOH[DPV FRP LV DQ RQOLQH SODWIRUP WKDW RIIHUV D ZLGH UDQJH RI VHUYLFHV UHODWHG WR FHUWLILFDWLRQ H[DP SUHSDUDWLRQ 7KH SODWIRUP SURYLGHV DFWXDO TXHVWLRQV H[DP GXPSV DQG SUDFWLFH WHVWV WR KHOS LQGLYLGXDOV SUHSDUH IRU YDULRXV FHUWLILFDWLRQ H[DPV ZLWK FRQILGHQFH +HUH DUH VRPH NH\ IHDWXUHV DQG VHUYLFHV RIIHUHG E\ .LOOH[DPV FRP
$FWXDO ([DP 4XHVWLRQV .LOOH[DPV FRP SURYLGHV DFWXDO H[DP TXHVWLRQV WKDW DUH H[SHULHQFHG LQ WHVW FHQWHUV 7KHVH TXHVWLRQV DUH XSGDWHG UHJXODUO\ WR HQVXUH WKH\ DUH XS WR GDWH DQG UHOHYDQW WR WKH ODWHVW H[DP V\OODEXV %\ VWXG\LQJ WKHVH DFWXDO TXHVWLRQV FDQGLGDWHV FDQ IDPLOLDUL]H WKHPVHOYHV ZLWK WKH FRQWHQW DQG IRUPDW RI WKH UHDO H[DP
([DP 'XPSV .LOOH[DPV FRP RIIHUV H[DP GXPSV LQ 3') IRUPDW 7KHVH GXPSV FRQWDLQ D FRPSUHKHQVLYH FROOHFWLRQ RI TXHVWLRQV DQG DQVZHUV WKDW FRYHU WKH H[DP WRSLFV %\ XVLQJ WKHVH GXPSV FDQGLGDWHV FDQ HQKDQFH WKHLU NQRZOHGJH DQG LPSURYH WKHLU FKDQFHV RI VXFFHVV LQ WKH FHUWLILFDWLRQ H[DP
3UDFWLFH 7HVWV .LOOH[DPV FRP SURYLGHV SUDFWLFH WHVWV WKURXJK WKHLU GHVNWRS 9&( H[DP VLPXODWRU DQG RQOLQH WHVW HQJLQH 7KHVH SUDFWLFH WHVWV VLPXODWH WKH UHDO H[DP HQYLURQPHQW DQG KHOS FDQGLGDWHV DVVHVV WKHLU UHDGLQHVV IRU WKH DFWXDO H[DP 7KH SUDFWLFH WHVWV FRYHU D ZLGH UDQJH RI TXHVWLRQV DQG HQDEOH FDQGLGDWHV WR LGHQWLI\ WKHLU VWUHQJWKV DQG ZHDNQHVVHV
*XDUDQWHHG 6XFFHVV .LOOH[DPV FRP RIIHUV D VXFFHVV JXDUDQWHH ZLWK WKHLU H[DP GXPSV 7KH\ FODLP WKDW E\ XVLQJ WKHLU PDWHULDOV FDQGLGDWHV ZLOO SDVV WKHLU H[DPV RQ WKH ILUVW DWWHPSW RU WKH\ ZLOO UHIXQG WKH SXUFKDVH SULFH 7KLV JXDUDQWHH SURYLGHV DVVXUDQFH DQG FRQILGHQFH WR LQGLYLGXDOV SUHSDULQJ IRU FHUWLILFDWLRQ H[DPV
8SGDWHG &RQWHQW .LOOH[DPV FRP UHJXODUO\ XSGDWHV LWV TXHVWLRQ EDQN DQG H[DP GXPSV WR HQVXUH WKDW WKH\ DUH FXUUHQW DQG UHIOHFW WKH ODWHVW FKDQJHV LQ WKH H[DP V\OODEXV 7KLV KHOSV FDQGLGDWHV VWD\ XS WR GDWH ZLWK WKH H[DP FRQWHQW DQG LQFUHDVHV WKHLU FKDQFHV RI VXFFHVV
7HFKQLFDO 6XSSRUW .LOOH[DPV FRP SURYLGHV IUHH [ WHFKQLFDO VXSSRUW WR DVVLVW FDQGLGDWHV ZLWK DQ\ TXHULHV RU LVVXHV WKH\ PD\ HQFRXQWHU ZKLOH XVLQJ WKHLU VHUYLFHV 7KHLU FHUWLILHG H[SHUWV DUH DYDLODEOH WR SURYLGH JXLGDQFH DQG KHOS FDQGLGDWHV WKURXJKRXW WKHLU H[DP SUHSDUDWLRQ MRXUQH\
'PS .PSF FYBNT WJTJU IUUQT LJMMFYBNT DPN WFOEPST FYBN MJTU
.LOO \RXU H[DP DW )LUVW $WWHPSW *XDUDQWHHG
View Practice Questions »